- 61. 10 women can complete a work in 8 days and 10 children take 12 days to complete the work. How many days will 6 women and 3 children together take to complete the work?
A.7
B.10
C.8
D.9
Answer & Explanation
Answer: Option B
Explanation:1 women’s 1 day’s work = 1/8/10 = 1/80
1 child’s 1 day’s work = 1/12/10 = 1/120
6 women’s 1 day’s work = 1/80 × 6 = 3/40
3 children’s 1 day’s work = 1/120 × 3 = 1/40
6 women’s + 3 children’s 1 day’s work = 3 /40 + 1/40 = 1/10
Therefore, they will finish the whole work in 10 days.
View Answer
- 62. 9 children can complete a piece of work in 360 days; 18 men can complete the same piece of work in 72 days and 12 women can complete it in 162 days. In how many days can 4 men, 12 women and 10 children together complete the piece of work?
A.68 days
B.81 days
C.96 days
D.124 days
Answer & Explanation
Answer: Option B
Explanation:1 child’s 1 day’s work = 1/360 ×9 = 1/3240
10 children’s 1 day’s work = 1/324
1 man’s 1 day’s work = 1/72 × 18 = 1/1296
4 men’s 1 day’s work = 1 ×4/1296 = 1/324
12 women’s 1 day’s work = 1/162 given
Then, (4 men + 12 women + 10 children)’s 1 day’s work = 1/324 + 1/162 + 1/324
= 1/324 + 2/324 + 1/324 = 4/324 = 1/81
Therefore, the required No. of days = 81 days.
View Answer
- 63. 9 men working 7 hours a day can complete a piece of work in 15 days. How many days can 6 men working for 9 hours a day, complete the same piece of work?
A.15 ¾ days
B.16 days
C.16 ¾ days
D.17 ½ days
Answer & Explanation
Answer: Option D
Explanation:1 work done = 9 × 7 × 15
9 × 7 × 15 = 6 × 9 × ? days
? days = 9 × 7 × 15/6 × 9
= 35/2 = 17 ½ days.
View Answer
- 64. A man, a woman and a boy can together complete a piece of work in 3 days. If a man alone can do it in 6 days and a boy alone in 18 days, how long will a woman take to complete the work?
A.9 days
B.21 days
C.24 days
D.27 days
Answer & Explanation
Answer: Option A
Explanation:(1 Man + 1 woman + 1 boy)’s 1day’s work = 1/3
1 man’s 1 day work = 1/6
1boy’s 1 day’s work = 1/18
(1 Man + 1 boy) ‘s 1 day’s work = 1/6 + 1/18 = 2/9
Therefore, 1 woman’s 1 day’s work = 1/3 – 2/9 = 3-2/9 = 1/9
Therefore, the woman alone can finish the work in 9 days.
View Answer
- 65. 8 men can do a piece of work in 12 days. 4 women can do it in 48 days and 10 children can do it in 24 days. In how many days can 10 men, 4 women and 10 children together complete the piece of work?
A.5 days
B.15 days
C.28 days
D.6 days
Answer & Explanation
Answer: Option D
Explanation:1 man’s 1 day’s work = 1/8 × 12 = 1/96
10 men’s 1 day’s work = 1 × 10/96 = 5/48
1 woman’s 1 day’s work = 1/192
4 women’s 1 day’s work = 1/192 × 4 = 1/48
1 child’s 1 day’s work = 1/240
10 children’s 1 day’s work = 1/24
Therefore, (10 men + 4 women + 10 children)’s 1 day’s work = 5/48 + 1/48 + 1/24
= 8/48 =1/6
The required No. of days = 6 days
View Answer
To whom this Time and Work Questions and Answers section is beneficial?
Students can learn and improve on their skillset for using Verbal Ability effectively and can also prepare for competitive examinations like...
- All I.B.P.S and Public Sector Bank Competitive Exam
- Common Aptitude Test (CAT) Exams
- UPSC Paper-II or CSAT Exams
- SSC Competitive Exams
- Defence Competitive Exams
- L.I.C / G.I.C AO and Clerk Competitive Exams
- Railway Competitive Exam
- University Grants Commission (UGC)
- Career Aptitude Test (IT Companies) and etc.