- 71. A works twice as fast as B. if both of them can together finish a piece of work in 12 days, then B alone can do it in
A.24 days
B.27 days
C.36 days
D.48 days
Answer & Explanation
Answer: Option C
Explanation:B = 2A
2A × A/3A = 12
2A/3 = 12
A = 18 days
B = 2 × 18 = 36 days
Therefore, B alone can finish the work in 36 days.
View Answer
- 72. A man, a woman and a boy can complete a job in 3 days, 4 days and 12 days respectively. How many boys must assist 1 man and 1 woman to complete the job in 1/4th of a day?
A.10
B.41
C.31
D.21
Answer & Explanation
Answer: Option B
Explanation:1 man’s 1 day’s work = 1/3, ¼ day’s work = 1/3 × ¼ = 1/12
1 woman’s 1 day’s work = ¼, ¼ day’s work = ¼ × ¼ = 1/16
1 boy’s 1 day’s work = 1/12, ¼ day’s work = 1/12 × ¼ = 1/48
Let ‘x’ be the No. of boys required.
Then, (1 man + 1 woman + x boy)’s ¼ day’s work 1/12 + 1/16 + x/48 = 1
= (4 + 3 + x)/48 = 1
i.e. 7 + x= 48 and x = 41.
View Answer
- 73. A does 4/5th of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
A.23 days
B.37 days
C.37 ½ days
D.40 days
Answer & Explanation
Answer: Option C
Explanation:A can finish the whole work in 20 × 5/4 days = 25 days
A and B together finish the whole work in 5 × 3 days = 15 days
Therefore, B can finish the whole work in 25 B/ 25 + B = 15
25 B = 15 ( 25 + B)= 375 + 15B
10B = 375 and B = 375/10 = 37 ½ days.
View Answer
- 74. A can do 1/4th part of the work in 10 days, B can do 40% of the work in 40 days and C can do 1/3rd of the work in 13 days. Who will complete the work first?
A.A
B.B
C.C
D.A and C both
Answer & Explanation
Answer: Option C
Explanation:The whole work is done by A in 4 × 10 = 40 days
B can do the whole work in 40/40 × 100 days = 100 days
C can do the whole work in 3 × 13 = 39 days.
Therefore, the 1st person to complete the work is C.
View Answer
- 75. A alone can finish a work in 10 days which B alone can finish in 15 days. If they work together and finish it, then out of a total wages of Rs.3000, A will get:
A.Rs.1200
B.Rs.1500
C.Rs. 1800
D.Rs.2000
Answer & Explanation
Answer: Option C
Explanation:Ratio of working days of A : B = 10 : 15
Therefore, their wages ratio = reverse ratio = 15 : 10
Therefore, A will get 15 units of ratio
Total ratio = 25
1 unit of ratio =3000/25 = 120
So, A’s amount = 120 × 15 = Rs.1800.
View Answer
To whom this Time and Work Questions and Answers section is beneficial?
Students can learn and improve on their skillset for using Verbal Ability effectively and can also prepare for competitive examinations like...
- All I.B.P.S and Public Sector Bank Competitive Exam
- Common Aptitude Test (CAT) Exams
- UPSC Paper-II or CSAT Exams
- SSC Competitive Exams
- Defence Competitive Exams
- L.I.C / G.I.C AO and Clerk Competitive Exams
- Railway Competitive Exam
- University Grants Commission (UGC)
- Career Aptitude Test (IT Companies) and etc.