- 51. A cistern is fille in 8 hours and it takes 12 hours when there is a leak in its bottom. If the cistern is full, in what time shall the leak empty it?
A.22 hours
B.21 hours
C.24 hours
D.23 hours
Answer & Explanation
Answer: Option C
Explanation:work done by 1 hour by filling pipe = 1/8
work done by 1 hour by the leak and the filling pipe =1/12
work done by 1 hour by the leak = 1/8 – 1/12 =1/24
Hence the leak can empty it in 24 hours.
View Answer
- 52. A and B working saperately can do a piece of work in 12 and 18 hours respectively. If they work for 6 hour alternately with B beginning, in how many hours will the work be completed?
A.9 hours
B.15 hours
C.13 ½ hours
D.12 ½ hours
Answer & Explanation
Answer: Option B
Explanation:A and B 2 hours work = 1/12 + 1/18 = 5/36
work done by A and B during 6 pairs
i.e 12 hours = 6 * 5/36 = 5/6
Remaining work = 1 – 5/6 = 1/6
1/6 of work and this work done by B only = 18* 1/6 = 3 hours
Hence the total time take is 15 hours
View Answer
- 53. A and B can do a piece of work in 48 days, A and C can do it in 60 days, b and c can do it 72 days. In what time can c alone do it?
A.84 days
B.84 ½ days
C.85 days
D.87 days
Answer & Explanation
Answer: Option C
Explanation:(A+B) 1 day work = 1/48
(B+C) 1 day work = 1/72
(A+C) 1 day work = 1/60
By adding 2(A+B+C) = 1/48 +1/72+1/60 = 37/720
(A+B+C) 1 day work = 37/1440
A 1 day work = 37/1440 – 1/72 = 17/1440 = 85 days (approximately)
View Answer
- 54. 8 boys complete a work in 14 days . In how many days will 14 boys complete that work?
A.14 days
B.7 days
C.8 days
D.6 days
Answer & Explanation
Answer: Option
Explanation:1 boy 1 day work = 14 × 8,
14 boys complete the work in 14 × 8/14= 8 days
View Answer
- 55. 16 boys or 24 girls can construct the wall in 6 days. the number of days that 8 boys and 12 girls Will take to construct?
A.7 days
B.14 days
C.6 days
D.8 days
Answer & Explanation
Answer: Option C
Explanation:16 boys =24 girls, 1 boy = 24/16 girls
1 boy = 6/4 girls
8 boys + 12 girls = 8 × 6/4 + 12 = 12 + 12 = 24 girls
6 days to complete the work
View Answer
To whom this Time and Work Questions and Answers section is beneficial?
Students can learn and improve on their skillset for using Verbal Ability effectively and can also prepare for competitive examinations like...
- All I.B.P.S and Public Sector Bank Competitive Exam
- Common Aptitude Test (CAT) Exams
- UPSC Paper-II or CSAT Exams
- SSC Competitive Exams
- Defence Competitive Exams
- L.I.C / G.I.C AO and Clerk Competitive Exams
- Railway Competitive Exam
- University Grants Commission (UGC)
- Career Aptitude Test (IT Companies) and etc.