- 36. A and B together can complete work in 4 days. A alone starts working and leaves it after working for 3 days completing only half of the work. In how many days it can be completed if the remaining job is undertaken by B?
A.4
B.8
C.5
D.6
Answer & Explanation
Answer: Option D
Explanation:(A+B) one day work =1/4
now A does half of the work in 3 days so A can complete the whole work in 6 days
A’s one day work =1/6
B’s one day work=1/4 - 1/6= 1/12
B alone can complete the work in 12 days so half of the work in 6 days
View Answer
- 37. In 12 pumps can raise 1218 tons of water in 11 days of 9 hrs each, how many pumps will raise 2030 tons of water in 12 days of 11 hrs each?
A.12
B.15
C.18
D.21
Answer & Explanation
Answer: Option B
Explanation:pumps work time
12 1218 99
x 2030 132
=> 1218/(912*99) = 2020/(x × 132)
=> x = 15 pumps
View Answer
- 38. A can do a piece of work in 5 days and B can do it in 6 days how long will they both work together to complete the work?
A.2 6/11
B.2 8/11
C.2 7/11
D.2 9/11
Answer & Explanation
Answer: Option B
Explanation:A’s one day work = 1/5
B’s one day work = 1/6
(A+B)’s one day work = 1/5 + 1/6 = 11/30 => time = 30/11 = 2 8/11 days
View Answer
- 39. If 3 men or 4 women can reap a field in 43 days how long will 7 men and 5 women take to reap it?
A.9
B.12
C.15
D.18
Answer & Explanation
Answer: Option B
Explanation:3 men reap 1/43 field in 1 day
1 man reap 1/(3 x 43)
4 women reap 1/43 field in 1 day
1 woman reap 1/(43 x 4)
7 men and 5 women reap (7/(3 x 43)+ 5/(4 x 43)) =1/12 in 1 day
7 men and 5 women will reap the field in 12 days
View Answer
- 40. 4 pipes can fill a reservoir in 15, 20, 30 and 60 hrs the first was opened at 6 am and 2nd at 7 am and thirds at 8 am and 4th at 9 am when will the reservoir be full?
A.6 hrs
B.7 hrs
C.8 hrs
D.9 hrs
Answer & Explanation
Answer: Option B
Explanation:let time be t hrs after 6 am
t/15 + (t-1)/30 + (t-2)/30 + (t-3)/60 =1
t = 7 hrs
View Answer
To whom this Time and Work Questions and Answers section is beneficial?
Students can learn and improve on their skillset for using Verbal Ability effectively and can also prepare for competitive examinations like...
- All I.B.P.S and Public Sector Bank Competitive Exam
- Common Aptitude Test (CAT) Exams
- UPSC Paper-II or CSAT Exams
- SSC Competitive Exams
- Defence Competitive Exams
- L.I.C / G.I.C AO and Clerk Competitive Exams
- Railway Competitive Exam
- University Grants Commission (UGC)
- Career Aptitude Test (IT Companies) and etc.