- 26. A is thrice good a workman as B and therefore is able to finish a job in 60 days less than B. Working together they can do it in?
A.20
B.22 ½
C.25
D.30
Answer & Explanation
Answer: Option B
Explanation:Ratio of times by A and B= 1:3
difference of time is 2 days B takes 3 days if diff of time is 60 days B takes 3/2 *60 =90 days
A’s 1day work is=1/30
B’s 1 day work =1/90
(A+B )’s one day work is=1/90 +1/30 =2/45
together can do work in 45/2 = 22 ½ days
View Answer
- 27. A is 30% more efficient than B. How much time will they working together take to complete a job which A alone could have done in 23 days?
A.11
B.13
C.20 3/17
D.None of these
Answer & Explanation
Answer: Option B
Explanation:Ratio of times taken by A and B= 100:130 =10:13
suppose B takes x days to work the 10:13::23:x =>x=23 x 13/10 = 299/10
A’s one day work = 1/23 and B’s is 10/299
Then A+B ‘s work = 1/23 + 10/299 = 23/299 =1/13 => 13 days
View Answer
- 28. A can do a work in 15 days and B in 20 days. If they work on it together for 4 days then the fraction of the work that is left is?
A.1/4
B.1/10
C.7/15
D.8/15
Answer & Explanation
Answer: Option D
Explanation:A’s one day work = 1/15
B’s one day work = 1/20
(A+B )’s one day work is = 1/15 +1/20 = 7/60
their 4 days work = 4 x 7/60 = 7/15
Remaining work = 8/15
View Answer
- 29. X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days how long will they work together take to complete the work?
A.13 1/3
B.15
C.20
D.56
Answer & Explanation
Answer: Option A
Explanation:Work done by x in 8 days= 8/40 = 1/5
remaining work= 4/5
4/5 work is done by Y in 16 days
whole work is done by Y in 16*5/4 = 20 days
X’s 1 day work =1/40
Y’s 1 day work =1/20
(X+Y)’s 1 day work=1/40 +1/20 = 3/40 = 13 1/3
View Answer
- 30. A alone can complete a work in 16 days and B alone can complete in 12 days. Starting with A they work on alternate days. The total work will be completed in?
A.12
B.13
C.13 5/7
D.13 ¾
Answer & Explanation
Answer: Option D
Explanation:(A+B)’s 2 day work = 1/16 + 1/12 = 7/18
work done in 6 pairs of days=7/48 x 6 = 7/8
remaining work = 1/8
work done by A on 13th day =1/16 remaining work = 1/16
on 14th day its B turn 1/12 work is done by B in 1 day 1/16 work is done by B in 12 x 1/16 = 3/4 day
total time taken =13 ¾ days
View Answer
To whom this Time and Work Questions and Answers section is beneficial?
Students can learn and improve on their skillset for using Verbal Ability effectively and can also prepare for competitive examinations like...
- All I.B.P.S and Public Sector Bank Competitive Exam
- Common Aptitude Test (CAT) Exams
- UPSC Paper-II or CSAT Exams
- SSC Competitive Exams
- Defence Competitive Exams
- L.I.C / G.I.C AO and Clerk Competitive Exams
- Railway Competitive Exam
- University Grants Commission (UGC)
- Career Aptitude Test (IT Companies) and etc.