61. 10 women can complete a work in 8 days and 10 children take 12 days to complete the work. How many days will 6 women and 3 children together take to complete the work? |
||||||||
View Answer Discuss in Forum
|
62. 9 children can complete a piece of work in 360 days; 18 men can complete the same piece of work in 72 days and 12 women can complete it in 162 days. In how many days can 4 men, 12 women and 10 children together complete the piece of work? |
||||||||
View Answer Discuss in Forum
|
63. 9 men working 7 hours a day can complete a piece of work in 15 days. How many days can 6 men working for 9 hours a day, complete the same piece of work? |
||||||||
View Answer Discuss in Forum
|
64. A man, a woman and a boy can together complete a piece of work in 3 days. If a man alone can do it in 6 days and a boy alone in 18 days, how long will a woman take to complete the work? |
||||||||
View Answer Discuss in Forum
|
65. 8 men can do a piece of work in 12 days. 4 women can do it in 48 days and 10 children can do it in 24 days. In how many days can 10 men, 4 women and 10 children together complete the piece of work? |
||||||||
View Answer Discuss in Forum
|
66. 8 men can dig a pit in 20 days. If a man works half as much again a s a boy, then 4 men and 9 boys can dig a similar pit in: |
||||||||
View Answer Discuss in Forum
|
67. A man and a boy complete a work together in 24 days. If for the last 6 days man alone does the work then it is completed in 26 days. How long the boy will take to complete the work alone? |
||||||||
View Answer Discuss in Forum
|
68. A, B and C completed a piece of work costing Rs.1800. A worked for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio 5 : 6 : 4, how much amount will be received by A? |
||||||||
View Answer Discuss in Forum
|
69. 12 men take 36 days to do a work while 12 women complete 3/4th of the same work in 36 days. In how many days 10 men and 8 women together will complete the same work? |
||||||||
View Answer Discuss in Forum
|
70. A is thrice as good a workman as B and therefore is able to finish a job in 60 days less than B. working together, they can do it in |
||||||||
View Answer Discuss in Forum
|